| Tabulation of Bids | Project Number: 4980 | Sheet 1 of 1 | |||||||
| Kansas Turnpike Authority | Subject: Microsurfacing | ||||||||
| Location: Topeka Service Area MP 188 | Date: June 17, 2008 | ||||||||
| Name of Bidder | Vance Bros. | Ballou Construction, Inc | |||||||
| Engineer's | |||||||||
| Address | 5201 Brighton | PO Box 2300 | Estimate | ||||||
| City, State, Zip | Kansas City, MO 64130 | Salina, KS 67402 | |||||||
| Item | Quantity | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount |
| 1 | |||||||||
| Mobilization | Lump Sum | $5,000.00 | $5,000.00 | $20,000.00 | $20,000.00 | $0.00 | $10,000.00 | $10,000.00 | |
| 15,550 | |||||||||
| Microsurfacing (Area 1) | Sq. Yds | $3.59 | $55,824.50 | $4.75 | $73,862.50 | $0.00 | $3.00 | $46,650.00 | |
| 3,440 | |||||||||
| Microsurfacing (Area 2) | Sq. Yds. | $3.59 | $12,349.60 | $4.75 | $16,340.00 | $0.00 | $5.00 | $17,200.00 | |
| 1 | |||||||||
| Traffic Control | Lump Sum | $5,000.00 | $5,000.00 | $7,500.00 | $7,500.00 | $0.00 | $5,000.00 | $5,000.00 | |
| GRAND TOTAL | $78,174.10 | $117,702.50 | $78,850.00 | ||||||
| Bid Packets Mailed to 3 Contractors/Suppliers | |||||||||